Beamline Frontend - Delivery record
Mask and Absorber | X-Y Slits | Screen Monitor
Synchrotron Facility | Beamline | Completion Date | Equipment Supplied | MAX IV (Sweden) | 5.0 GeV ring (three beamlines) | Delivery in 2017 | Front Mask - 1 |
---|---|---|---|
Front Mask - 2 | |||
Absorber and Beam Position Monitor | |||
Main Mask | |||
Water cooled Screen Monitor | |||
Beam Shutter | MAX IV (Sweden) | 1.5 GeV ring (all beamlines) | March 2016 | Front Mask - 1 |
Front Mask - 2 | |||
Absorber and Beam Position Monitor | |||
Main Mask | |||
Water cooled Screen Monitor | |||
Beam Shutter | |||
Saga Light Source (Japan) | BL7 | March 2010 | Absorber |
Beam Shutter | |||
Front Mask - 1 | |||
Front Mask - 2 | |||
Chamber for Vacuum Pumps | |||
Beam Pipe through wall | |||
Chamber for Be Window | |||
Saga Light Source (Japan) | BL10 | January 2009 | Front Mask - 1 |
Front Mask - 2 | |||
Absorber and Beam Position Monitor | |||
Main Mask | |||
Water cooled Screen Monitor | |||
Beam Shutter | |||
Saga Light Source (Japan) | BL11 | January 2009 | Front Mask - 1 |
Front Mask - 2 | |||
Absorber and Beam Stopper | |||
Beam Pipe through wall | |||
Water cooled 4 blades Slit | |||
PF-AR Storage Ring (Japan) | AR-NE3 | July 2008 | Layout |
Water cooled Mask | |||
X-Y Slits | |||
SPring-8 (Japan) | BL12XU | March 2008 | X-Y Slit |
Fixed Mask | |||
Absorber | |||
Front Slit |
Updated January 2017